Primavera Online Test Home > Courses Questions on Primavera 1. Which of the following fields must be unique when inputting data in Primavera? Project Description Project name Project Manager Project ID 2. How are costs computed in Primavera? It uses similar projects in its database and uses a 3-point estimate to compute the cost By assigning resources and costs in Activities Primavera uses a Rough order of Magnitude estimate to determine project costs Primavera uses Monte Carlo Simulation to compute costs 3. Which of these statements is true regarding Enterprise Project Structure in Primavera? It represents the filling system for Projects. It is a component of the client server It is configured during installation and cannot be modified afterwards Activities are the lowest level of the Work Breakdown Structure 4. Why is it important to assign the responsible managers to the Enterprise Project Structure nodes? It links the EPS to the OBS element It helps to define the code of account identifier. It links the WBS to the EPS element It helps with configuration management 5. Some activities in the project plan are shown as red while others are shown as blue, how would you explain this to your customer if asked why? Activities shown in red are those that would be handled by contractors while those in blue are the activities handled by the internal project team. The activities shown in red are activities that need special types of resources on the project. Activities that are shown in red are on the critical path, if they are delayed they have the potential to delay the project’s end date. Activities that are likely to finish faster are in red while those that would finish slower are in blue. Loading … Question 1 of 5