MS Project Online Test Home > Courses Questions on MS Project 1. Which of these predecessor types would you use to describe the sequence of activities used to describe the handing over of a baton in a relay race? Finish to Finish Start to Start Finish to Start Start to Finish 2. Which of these components is not found in Microsoft Project? WBS Numbers Summary Tasks Pivots Milestones 3. Which TAB would you use to show only the milestones of the project? View Project Task Format 4. What are the types of constraints available in MS Project? As soon as Possible All of the Above As late as Possible None of the Above 5. You have just completed your schedule using MS Project and it has been approved by management, what is the next thing you should do? Set a benchmark Set a baseline Set milestones Perform resource levelling Loading … Question 1 of 5