MS Project Online Test Home > Courses Questions on MS Project 1. You have just completed your schedule using MS Project and it has been approved by management, what is the next thing you should do? Set a benchmark Set a baseline Perform resource levelling Set milestones 2. Which TAB would you use to show only the milestones of the project? Format Project Task View 3. Which of these components is not found in Microsoft Project? Summary Tasks WBS Numbers Pivots Milestones 4. What are the types of constraints available in MS Project? As late as Possible All of the Above As soon as Possible None of the Above 5. Which of these predecessor types would you use to describe the sequence of activities used to describe the handing over of a baton in a relay race? Finish to Start Finish to Finish Start to Start Start to Finish Loading … Question 1 of 5