MS Project Online Test Home > Courses Questions on MS Project 1. Which TAB would you use to show only the milestones of the project? Format View Project Task 2. What are the types of constraints available in MS Project? As soon as Possible None of the Above All of the Above As late as Possible 3. Which of these predecessor types would you use to describe the sequence of activities used to describe the handing over of a baton in a relay race? Finish to Start Start to Start Finish to Finish Start to Finish 4. You have just completed your schedule using MS Project and it has been approved by management, what is the next thing you should do? Set a baseline Set a benchmark Set milestones Perform resource levelling 5. Which of these components is not found in Microsoft Project? Pivots Summary Tasks WBS Numbers Milestones Loading … Question 1 of 5